Phase 1 Project planning checklist
| Migration preparation activities have commenced | |
| Migration project stakeholders have been identified | |
| Migration project stakeholders have been engaged | |
| Preliminary investigation is complete | |
| The records are eligible for transfer under State Records' s.29 guidelines | |
| Information gathering is complete | |
| The migration project is justified | |
| The migration project is supported | |
| The migration project scope has been defined | |
| The migration project can be resourced | |
| The project plan has been drafted | |
| The project plan has been approved | |
| Risk and issue management in place | |
| Project governance has been established | 
Phase 2 Migration planning checklist
| The migration scenario has been analysed | |
| Assessment requirements have been determined | |
| Migration assessment outputs have been analysed | |
| Migration requirements have been determined | |
| Action on source records has been determined | |
| Any additional risks have been identified | |
| The migration strategy has been determined | |
| The migration can be resourced | |
| Migration assessment is complete | |
| The migration plan has been drafted | |
| The migration plan has been approved | |
| The migration schedule is in place | |
| Roles and responsibilities have been defined | |
| Risks and issues have been monitored and managed | 
Phase 3 Migration checklist
| Migration preparation activities have commenced | |
| Pre-migration testing has commenced | |
| Any errors from pre-migration testing have been identified and fixed | |
| Pre-migration testing is complete | |
| Migration preparation activities are complete | |
| Any required changes to the migration plan have been made | |
| Records are migrated to the Digital Archives repository using defined workflows | |
| Post-migration testing has commenced | |
| Any errors from post-migration testing have been identified and fixed | |
| Post-migration testing is complete | |
| The migration is validated | |
| Risks and issues have been monitored and managed | 
Phase 4 Project completion checklist
| State Records has taken formal control of the records | |
| Planning for action on source records is in place | |
| If required, source records have been deleted under authorisation | |
| Project deliverables have been assessed | |
| Project outcomes have been assessed | |
| Risks and issues have been monitored and managed | |
| Formal sign off for project closure from key project stakeholders has been done | |
| Any relevant documentation and reports created during the migration project have been shared | |
| Documentation and reports created and shared during the migration project are captured as records | |
| The migration project is closed | 
 
        